Directions to Mine |
East on Hwy 280 into Childesburg, Cros river bridge turn right at 2nd light on Co. Road. Go 10 miles, go left on Co Rd 34. Go 12 miles left on Rock Ridge Lane.
|
Parties
Name
|
ROCK PRODUCTS, LLC
|
Role
|
Operator
|
Start Date
|
2007-06-12
|
End Date
|
2012-10-22
|
|
Name
|
A Team Mining LLC
|
Role
|
Operator
|
Start Date
|
2012-10-23
|
|
Name
|
Rock Products Inc
|
Role
|
Operator
|
Start Date
|
1979-01-01
|
End Date
|
2007-06-11
|
|
Name
|
Jerry Lewis; Brad Stevens
|
Role
|
Current Controller
|
Start Date
|
2012-10-23
|
|
Name
|
A Team Mining LLC
|
Role
|
Current Operator
|
|
Accidents
Accident Date |
2013-01-10
|
Degree Inhury |
DAYS AWAY FROM WORK ONLY
|
Accident Type |
Caught in, under or between NEC
|
Ocupation |
Front-end loader, Scraper-loader operator, Pan operator, Payloader, Scraper rig operator
|
Narrative |
EE had come out of the loader to help co-worker replace blow bars in crusher. They were standing on bars that were blocked but not secure enough. EE was trying to get off crusher when the weight shifted and his right foot and leg was caught by a blow bar.
|
|
Inspections
Start Date |
2016-05-17
|
End Date |
2016-05-18
|
Activity |
Spot Inspection
|
Number Inspectors |
1
|
Total Hours |
2.25
|
|
Start Date |
2015-09-16
|
End Date |
2015-09-17
|
Activity |
Mine Idle Activity
|
Number Inspectors |
1
|
Total Hours |
9.5
|
|
Start Date |
2015-04-08
|
End Date |
2015-04-08
|
Activity |
Special Emphasis Programs
|
Number Inspectors |
1
|
Total Hours |
1.75
|
|
Start Date |
2015-04-07
|
End Date |
2015-04-16
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
2
|
Total Hours |
38
|
|
Start Date |
2014-12-16
|
End Date |
2014-12-16
|
Activity |
Spot Inspection
|
Number Inspectors |
1
|
Total Hours |
3.5
|
|
Start Date |
2014-12-10
|
End Date |
2014-12-11
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
19.25
|
|
Start Date |
2014-12-10
|
End Date |
2014-12-11
|
Activity |
Special Emphasis Programs
|
Number Inspectors |
1
|
Total Hours |
.75
|
|
Start Date |
2014-10-02
|
End Date |
2014-10-02
|
Activity |
Compliance Follow-up Inspection
|
Number Inspectors |
1
|
Total Hours |
6
|
|
Start Date |
2014-09-29
|
End Date |
2014-09-30
|
Activity |
Compliance Follow-up Inspection
|
Number Inspectors |
1
|
Total Hours |
6.25
|
|
Start Date |
2014-09-02
|
End Date |
2014-09-04
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
19
|
|
Start Date |
2014-01-28
|
End Date |
2014-01-28
|
Activity |
Compliance Follow-up Inspection
|
Number Inspectors |
1
|
Total Hours |
15
|
|
Start Date |
2014-01-08
|
End Date |
2014-01-13
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
26
|
|
Start Date |
2013-01-14
|
End Date |
2013-01-16
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
24
|
|
Start Date |
2012-05-16
|
End Date |
2012-05-16
|
Activity |
Mine Idle Activity
|
Number Inspectors |
1
|
Total Hours |
6
|
|
Start Date |
2012-01-23
|
End Date |
2012-01-23
|
Activity |
Compliance Follow-up Inspection
|
Number Inspectors |
1
|
Total Hours |
6
|
|
Start Date |
2012-01-05
|
End Date |
2012-01-06
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
16
|
|
Start Date |
2011-08-01
|
End Date |
2011-08-01
|
Activity |
Compliance Follow-up Inspection
|
Number Inspectors |
1
|
Total Hours |
2.5
|
|
Start Date |
2011-07-14
|
End Date |
2011-07-14
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
6.5
|
|
Start Date |
2011-03-16
|
End Date |
2011-03-17
|
Activity |
Regular Safety and Health Inspection
|
Number Inspectors |
1
|
Total Hours |
9
|
|
Start Date |
2009-04-29
|
End Date |
2009-04-30
|
Activity |
Mine Idle Activity
|
Number Inspectors |
1
|
Total Hours |
1
|
|
Productions
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2015
|
Annual Hours
|
2145
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
9
|
Avg. Employee Hours
|
238
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2015
|
Annual Hours
|
1489
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
4
|
Avg. Employee Hours
|
372
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2014
|
Annual Hours
|
6314
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
4
|
Avg. Employee Hours
|
1579
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2014
|
Annual Hours
|
5700
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
3
|
Avg. Employee Hours
|
1900
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2013
|
Annual Hours
|
10454
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
7
|
Avg. Employee Hours
|
1493
|
|
Sub-Unit Desc
|
MILL OPERATION/PREPARATION PLANT
|
Year
|
2013
|
Annual Hours
|
366
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
366
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2013
|
Annual Hours
|
4299
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
2150
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2012
|
Annual Hours
|
4288
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
6
|
Avg. Employee Hours
|
715
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2012
|
Annual Hours
|
500
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
250
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2011
|
Annual Hours
|
8570
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
3
|
Avg. Employee Hours
|
2857
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2010
|
Annual Hours
|
4142
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
4
|
Avg. Employee Hours
|
1036
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2009
|
Annual Hours
|
216
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
216
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2009
|
Annual Hours
|
216
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
216
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2008
|
Annual Hours
|
5040
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
4
|
Avg. Employee Hours
|
1260
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2008
|
Annual Hours
|
2760
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
1380
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2007
|
Annual Hours
|
9600
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
5
|
Avg. Employee Hours
|
1920
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2007
|
Annual Hours
|
3840
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
1920
|
|
Sub-Unit Desc
|
STRIP, QUARY, OPEN PIT
|
Year
|
2006
|
Annual Hours
|
6100
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
4
|
Avg. Employee Hours
|
1525
|
|
Sub-Unit Desc
|
MILL OPERATION/PREPARATION PLANT
|
Year
|
2006
|
Annual Hours
|
160
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
1
|
Avg. Employee Hours
|
160
|
|
Sub-Unit Desc
|
OFFICE WORKERS AT MINE SITE
|
Year
|
2006
|
Annual Hours
|
2120
|
Annual Coal Prod
|
0
|
Avg. Annual Empl.
|
2
|
Avg. Employee Hours
|
1060
|
|
|