343167904
|
0418600
|
2018-05-16
|
265 TEAGUE COURT, AUBURN, AL, 36832
|
|
Inspection Type |
Planned
|
Scope |
Complete
|
Safety/Health |
Safety
|
Close Conference |
2018-05-16
|
Emphasis |
L: AUTOSUP, L: FORKLIFT, P: AUTOSUP
|
Case Closed |
2018-05-30
|
|
340430818
|
0418600
|
2015-02-25
|
265 TEAGUE COURT, AUBURN, AL, 36832
|
|
Inspection Type |
Planned
|
Scope |
Partial
|
Safety/Health |
Health
|
Close Conference |
2015-02-25
|
Emphasis |
P: HINOISE, L: HINOISE
|
Case Closed |
2015-04-13
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Other |
Standard Cited |
19100095 L01 |
Issuance Date |
2015-03-18 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2015-04-13 |
Nr Instances |
1 |
Nr Exposed |
8 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1910.95(l)(1): The employer did not post of copy of 29 CFR 1910.95 in the workplace. (a) Facility: On or about February 25, 2015; the employer failed to post a copy of the hearing conservation standard where employees exposed over the 85dBa action level have ready access to it. |
|
|
339674756
|
0418600
|
2014-04-10
|
265 TEAGUE COURT, AUBURN, AL, 36832
|
|
Inspection Type |
Complaint
|
Scope |
Complete
|
Safety/Health |
Safety
|
Close Conference |
2014-04-11
|
Emphasis |
L: FORKLIFT, L: FALL, L: AUTOSUP, N: AMPUTATE
|
Case Closed |
2014-10-02
|
Related Activity
Type |
Complaint |
Activity Nr |
879413 |
Safety |
Yes |
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Serious |
Standard Cited |
19100147 A02 II |
Issuance Date |
2014-08-25 |
Abatement Due Date |
2014-09-19 |
Current Penalty |
2500.0 |
Initial Penalty |
4410.0 |
Final Order |
2014-09-19 |
Nr Instances |
19 |
Nr Exposed |
40 |
Gravity |
10 |
FTA Current Penalty |
0.0 |
|
Citation ID |
01002 |
Citaton Type |
Serious |
Standard Cited |
19100147 F03 II |
Issuance Date |
2014-08-25 |
Abatement Due Date |
2014-09-19 |
Current Penalty |
0.0 |
Initial Penalty |
4410.0 |
Final Order |
2014-09-19 |
Nr Instances |
1 |
Nr Exposed |
3 |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1910.147(f)(3)(ii): Group lockout or tagout devices were not used in accordance with procedures required by 29 CFR 1910.147(c)(4): a) On or about April 10, 2014 and times prior; Group Lockout/Tagout): The employer failed to ensure group lockout/Tagout procedures were followed when three employees were involved in a tool change on line 4, machine g, due to not having each employee having their personal lock installed on energy sources. |
|
Citation ID |
02001 |
Citaton Type |
Repeat |
Standard Cited |
19100147 C07 I |
Issuance Date |
2014-08-25 |
Abatement Due Date |
2014-09-19 |
Current Penalty |
6468.0 |
Initial Penalty |
10780.0 |
Final Order |
2014-09-19 |
Nr Instances |
1 |
Nr Exposed |
16 |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1910.147(c)(7)(i): The employer did not provide training to ensure that the purpose and function of the energy control program are understood by employees and that the knowledge and skills required for the safe application, usage, and removal of the energy controls are acquired by employees: a) On or about April 10, 2014 and times prior; control of hazardous energy (Lockout/Tagout - LOTO) program training: The employer failed to ensure LOTO training was presented in or translated to the native language of the Korean employees which created the opportunity for confusion in the material presented and the skills required for safe application, usage, and removal or energy controls during tool change and change over activities. CNJ, Inc., was previously cited for a violation of this occupational safety and health standard or its equivalent standard 29 CFR 1910.147(c)(7)(i) which was contained in OSHA inspection number 569640, citation number 01, item number 02 and was affirmed as a final order on January 8, 2013, with respect to a workplace location at 265 Teague Court, Auburn, Alabama. |
|
|
339130239
|
0418600
|
2013-06-17
|
265 TEAGUE COURT, AUBURN, AL, 36832
|
|
Inspection Type |
Complaint
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2013-06-17
|
Emphasis |
L: FORKLIFT
|
Case Closed |
2013-08-01
|
Related Activity
Type |
Complaint |
Activity Nr |
822863 |
Safety |
Yes |
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Serious |
Standard Cited |
19100219 F03 |
Issuance Date |
2013-06-27 |
Current Penalty |
1300.0 |
Initial Penalty |
1894.0 |
Final Order |
2013-07-16 |
Nr Instances |
1 |
Nr Exposed |
1 |
Gravity |
1 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1910.219(f)(3): Sprocket wheels and chains which were seven -7 feet or less above floors or platforms were not enclosed: a) At Paint Machine Number One: On or about June 17, 2013 and at times prior; the employer failed to ensure a cover over the chain and sprocket under the cooling machine had been replaced after maintenace was performed on the machine. |
|
|
335696407
|
0418600
|
2012-07-26
|
265 TEAGUE COURT, AUBURN, AL, 36832
|
|
Inspection Type |
Complaint
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2012-07-26
|
Emphasis |
N: AMPUTATE, L: FORKLIFT
|
Case Closed |
2013-03-07
|
Related Activity
Type |
Complaint |
Activity Nr |
456871 |
Safety |
Yes |
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Serious |
Standard Cited |
19100147 C06 I |
Issuance Date |
2013-01-04 |
Abatement Due Date |
2013-01-16 |
Current Penalty |
2448.0 |
Initial Penalty |
3500.0 |
Final Order |
2013-01-08 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: a) Lines 1-4's Robotic Arms: On or about July 27, 2012 and at times prior thereto, the employer did not evaluate its lockout tagout program, training, and written procedure, or evaluate the performance of its authorized employees in execution of the lockout tagout procedures which exposed employees to inadvertent start up and/or energy sources (e.g. electrical) of the system. |
|
Citation ID |
01002 |
Citaton Type |
Serious |
Standard Cited |
19100147 C07 I |
Issuance Date |
2013-01-04 |
Abatement Due Date |
2013-03-11 |
Current Penalty |
2448.0 |
Initial Penalty |
3500.0 |
Final Order |
2013-01-08 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1910.147(c)(7)(i): The employer did not provide adequate training to ensure that employees acquired the knowledge and skills required for the safe application, usage and removal of energy control devices: a) Lines 1-4's Robotic Arms: On or about July 27, 2012 and at times prior thereto, the employer did not ensure the authorized employees were trained to effectively affix lockout devices which exposed employees to inadvertent start up and/or energy sources (e.g. electrical) of the system. |
|
|
313884330
|
0418600
|
2009-11-09
|
265 TEAGUE CT., AUBURN, AL, 36832
|
|
Inspection Type |
Referral
|
Scope |
Partial
|
Safety/Health |
Health
|
Close Conference |
2009-11-10
|
Emphasis |
N: DUSTEXPL
|
Case Closed |
2010-05-17
|
Related Activity
Type |
Referral |
Activity Nr |
200459246 |
Health |
Yes |
|
Violation Items
Citation ID |
01001A |
Citaton Type |
Serious |
Standard Cited |
19101200 E01 |
Issuance Date |
2010-03-18 |
Abatement Due Date |
2010-03-23 |
Current Penalty |
1000.0 |
Initial Penalty |
1250.0 |
Nr Instances |
1 |
Nr Exposed |
32 |
Related Event Code (REC) |
Referral |
Gravity |
03 |
|
Citation ID |
01001B |
Citaton Type |
Serious |
Standard Cited |
19101200 G01 |
Issuance Date |
2010-03-18 |
Abatement Due Date |
2010-03-23 |
Nr Instances |
1 |
Nr Exposed |
32 |
Gravity |
03 |
|
Citation ID |
01001C |
Citaton Type |
Serious |
Standard Cited |
19101200 G01 |
Issuance Date |
2010-03-18 |
Abatement Due Date |
2010-03-23 |
Nr Instances |
1 |
Nr Exposed |
32 |
Gravity |
03 |
|
Citation ID |
02001 |
Citaton Type |
Other |
Standard Cited |
19100134 C01 |
Issuance Date |
2010-03-18 |
Abatement Due Date |
2010-04-13 |
Nr Instances |
1 |
Related Event Code (REC) |
Referral |
Gravity |
01 |
|
|
313884223
|
0418600
|
2009-10-26
|
265 PEAK COURT, AUBURN, AL, 36832
|
|
Inspection Type |
Complaint
|
Scope |
Complete
|
Safety/Health |
Safety
|
Close Conference |
2009-10-27
|
Emphasis |
N: AMPUTATE, S: AMPUTATIONS, S: NOISE, S: POWERED IND VEHICLE
|
Case Closed |
2010-10-21
|
Related Activity
Type |
Complaint |
Activity Nr |
206975534 |
Safety |
Yes |
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Serious |
Standard Cited |
19100022 A02 |
Issuance Date |
2010-04-14 |
Abatement Due Date |
2010-04-19 |
Current Penalty |
850.0 |
Initial Penalty |
1000.0 |
Nr Instances |
1 |
Nr Exposed |
7 |
Gravity |
02 |
|
Citation ID |
01002 |
Citaton Type |
Serious |
Standard Cited |
19100212 A01 |
Issuance Date |
2010-04-14 |
Abatement Due Date |
2010-04-19 |
Current Penalty |
1487.5 |
Initial Penalty |
1750.0 |
Nr Instances |
2 |
Nr Exposed |
2 |
Gravity |
05 |
|
Citation ID |
01003 |
Citaton Type |
Serious |
Standard Cited |
19100242 B |
Issuance Date |
2010-04-14 |
Abatement Due Date |
2010-04-19 |
Current Penalty |
1062.5 |
Initial Penalty |
1250.0 |
Nr Instances |
1 |
Nr Exposed |
1 |
Gravity |
03 |
|
Citation ID |
02001 |
Citaton Type |
Willful |
Standard Cited |
19100147 C01 |
Issuance Date |
2010-04-14 |
Abatement Due Date |
2010-07-30 |
Current Penalty |
23800.0 |
Initial Penalty |
28000.0 |
Nr Instances |
3 |
Nr Exposed |
4 |
Gravity |
10 |
|
Citation ID |
03001 |
Citaton Type |
Other |
Standard Cited |
19040029 B01 |
Issuance Date |
2010-04-14 |
Abatement Due Date |
2010-05-28 |
Current Penalty |
425.0 |
Initial Penalty |
500.0 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
00 |
|
|