Inspection Type |
Planned
|
Scope |
Complete
|
Safety/Health |
Safety
|
Close Conference |
2013-03-07
|
Emphasis |
L: FORKLIFT, L: EISAX, L: EISAOF, N: SSTARG12, P: SSTARG12
|
Case Closed |
2013-05-02
|
Violation Items
Citation ID |
01001A |
Citaton Type |
Serious |
Standard Cited |
19100215 A04 |
Issuance Date |
2013-04-05 |
Abatement Due Date |
2013-04-17 |
Current Penalty |
1800.0 |
Initial Penalty |
3000.0 |
Final Order |
2013-05-02 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1910.215(a)(4): Work rest(s) on grinding machinery were not adjusted closely to the wheel with a maximum opening of one-eighth inch: (a) On or about March 7, 2013 - 205 Butler Circle SW, Vernon, AL, Bay 2, an electric grinder Model# JBG-6A, Stock# 577101, S/N# 6425996, was not adjusted to one-eighth inch of the grinding wheel. |
|
Citation ID |
01001B |
Citaton Type |
Serious |
Standard Cited |
19100215 B09 |
Issuance Date |
2013-04-05 |
Abatement Due Date |
2013-04-17 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2013-05-02 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1910.215(b)(9): The distance between the abrasive wheel periphery(s) and the adjustable tongue or the end of the safety guard peripheral member at the top exceeded one-fourth inch: (a) On or about March 7, 2013 - 205 Butler Circle SW, Vernon, AL, Bay 2, an electric grinder Model# JBG-6A, Stock# 577101, S/N# 6425996, was not adjusted to one-fourth inch of the grinding wheel. |
|
Citation ID |
01002 |
Citaton Type |
Serious |
Standard Cited |
19100305 B01 II |
Issuance Date |
2013-04-05 |
Abatement Due Date |
2013-04-17 |
Current Penalty |
1575.0 |
Initial Penalty |
2625.0 |
Final Order |
2013-05-02 |
Nr Instances |
2 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1910.305(b)(1)(ii): Unused openings in boxes, cabinets, or fittings were not effectively closed: (a) On or about March 7, 2013 - 205 Butler Circle SW, Vernon, AL, Bay 1, unused openings in a circuit breaker panel were not effectively closed. (b) On or about March 7, 2013 - 205 Butler Circle SW, Vernon, AL, Bay 1, unused openings in a circuit breaker panel were not effectively closed. |
|
Citation ID |
02001 |
Citaton Type |
Other |
Standard Cited |
19100134 C02 I |
Issuance Date |
2013-04-05 |
Abatement Due Date |
2013-04-25 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2013-05-02 |
Nr Instances |
1 |
Nr Exposed |
2 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1910.134(c)(2)(i): Respirator users were not provided with the information contained in Appendix D to 29 CFR 1910.134 when the employer determined that any voluntary respirator use was permissible: (a) On or about March 7, 2013 - 205 Butler Circle SW, Vernon, AL, employees wearing SAS N95 respirators had not been provided a copy of Appendix D. |
|
|